Estimating large projects always comes with some degree of error, and project managers have always been trying to figure out how to deliver more accurate estimates. There are many techniques available; it can be overwhelming to choose the right one at times. Three point estimation is one such method. It has a rich history of usage across many different industries and types of organizations.
History of the PERT Method
Three point estimation can also be called the PERT method. PERT stands for Program (or Project) Evaluation and Review Technique. It was originally developed for the U.S. Navy Special Projects Office in 1957 during the U.S. Navy’s Polaris nuclear submarine project. It has also been used in other notable applications like the 1968 Winter Olympics that took place in Grenoble. And it continues to be used today in the aerospace industry and for other large projects.
What is the PERT Method?
The idea of three point estimation is quite simple. After breaking down work into smaller tasks, you evaluate each task separately. Instead of estimating that a task will take 10 hours, you allow for some uncertainty in the equation. With PERT, you come up with three numbers for each task:
1. Optimistic: (Low Estimate) This is the “happy path” where everything goes right and the task takes the minimum amount of time that it could take.
2. Most Likely: (Best Estimate) This is the best guess that you have, if all proceeds somewhat normally and there are a few bumps in the road, the task will take this long.
3. Pessimistic: (High Estimate) This is the worst case scenario, where everything goes wrong. You assume the worst and try to plan for it.
The PERT Method Formula
And while these three data points are useful by themselves, the additional benefit of the PERT method is the formula you use to determine the PERT estimate.
PERT ESTIMATE = (OPTIMISTIC + (4 * MOST LIKELY) + PESSIMISTIC) / 6
Essentially what this formula does is give more weight to the most likely number by multiplying it by four, but then balancing out the estimate by dividing it all by 6. This gives you an estimated number that is not simply the Most Likely number, but an estimate that balances the low, the high and the most likely.
Just because you have now calculated your PERT estimate doesn’t mean you should throw away your high and low values! Those inputs are still valuable when it comes to estimating time. Often it can be best to think in ranges when it comes to estimating projects, knowing the worst case and the best case can still be valuable information to take into account.
Calculating Standard Deviation
An optional element that can be added to the PERT methodology is calculating a standard deviation using your low, high, and most likely values. The standard deviation can be used as a measure of how much variation there is in your estimates. A higher number may indicate a greater degree of uncertainty in your estimate.
STANDARD DEVIATION = (PESSIMISTIC – OPTIMISTIC) / 6
Many teams will agree to a standard range that the standard deviation should fit into. In cases where your standard deviation does not fall in that range then it may be necessary to gather more information or make changes to your estimate in order to increase the level of certainty in your estimates.
For example, the range for completing a task may fall outside an agreed upon range of 1 to 5 meaning the task should be broken into subtasks to estimate with the agreed upon range. In this example let say the PESSIMISTIC = 40 hours and the OPTIMISTIC = 5 hours then 40-10 = 35 / 6 = 5.83. If that task was re-estimated with a PESSIMISTIC = 20 hours and the OPTIMISTIC = 5 hours then 20-10 = 10 / 6 = 1.67. Simple Estimate uses PERT which makes your estimation more accurate and using the Standard Deviation formula let’s you determine which areas of your estimate have the most uncertainty.
Benefits of Three Point Estimation
- Easier decision making with more helpful data points
- Make project stakeholders and/or clients happier
- Thinking in ranges rather than exact numbers
- Fewer surprises at the end of a project
- Higher employee satisfaction with more realistic expectations
Downsides of Three Point Estimation
- These are still subjective guesses and may still lack accuracy based on false assumptions
- Can be less accurate for smaller projects
- Can be tricky to calculate on huge projects with many variables if you don’t use Simple Estimate! We make it simple and automatic!
Our software Simple Estimate has the ability to estimate out of the box with One, Two, or Three point estimation techniques. In addition it can speed up the estimating process by pre-filling hourly rates for various roles in your agency or organization and allowing you to refine your own templates or partial templates that you can quickly start new projects from.
Three point estimation is one of the estimation tools you can use to gain valuable insights into your upcoming project and gain a larger degree of confidence than you would have with a single data point. The PERT methodology has been successfully used across many organizations and industries to plan projects since its invention in the 1950’s.
And while the PERT formula is helpful, it is always wise to remember that projects can still go awry, and so it is best to have plans in place when that happens. Have contingency plans in place for when things go wrong and build workplace expectations around understanding the estimating process and how it could be improved for your organization.
Simple Estimate is a tool designed for agencies and dev shops to make sense out of the estimating process.